ITERATION 2: Item entry and category column assignment
The goal of iteration 2 is to get a minimalistic version of the product in your hands. Functionally, we want you to be able to do the following:
- Add/Remove Sections
- Add/Remove Columns
- Add/Remove Items
- Assign items to categories
At the end of this iteration, the product will only support one view, but you will be able to configure that view using the above mentioned functions. Also, the screens should look much nicer than they do in their current incarnation. We will also be ramping up a new team member in this iteration and giving our deployment procedures their first try. Somewhere along in there, we will also try to enjoy Memorial day weekends and the graduations that accompany it
From the project plan, the iteration objectives are:
- Define requirements and design for a simple view
- Implement view with columns
- Deployment procedures defined and in use
- Setup group project infrastructure
- Team member ramp up